Water, Energy & Animal Welfare
Site ProgressEnergy system and radiant cooling
35–40% lower operating energy (estimate)
Each image is labelled Current Activity, Site Progress, Proposed Design or Reference Image.
How it is verified
- Milestone check before each payment
- Separate CSR account and reconciliation
- Utilisation and CA certificates
- Quarterly partner reports
Why this amount
₹4.31 Cr
A CO₂ heat pump with radiant cooling and thermal storage, at a combined COP of about 4.35. Costs come from Triveni Turbines, Agape and ABS.
| Cost line | Basis | Amount |
|---|---|---|
| CO₂ heat pump, 209 kW | Sourced | ₹212.00 L |
| Radiant cooling | Sourced | ₹63.60 L |
| Cold thermal storage | Sourced | ₹44.00 L |
| Hot-water storage | Sourced | ₹35.00 L |
| Project management, monitoring and reporting (3%) | Planning | ₹10.65 L |
| GST provision and rounding | Planning | ₹65.75 L |
| Indicative total | ₹4.31 Cr | |
Sourced: cost schedule or vendor quote. Planning: estimate pending final quotation. Forecast: calculated at published rates. Totals may differ slightly because of rounding.
- Schedule VII
- (iv)
- UN SDGs
- 6, 7, 11, 12, 15
- Trackable impact
- Reporting support
- Audit readiness
Related
More in this programme

Proposed DesignCapital
Rainwater harvesting and recharge
Five recharge structures, 12+ lakh litres a year
₹43.00 LDetails

Proposed DesignCapital
Native landscaping
10,484 sq ft irrigated by recycled water
₹67.00 LDetails

Proposed DesignCapital + programme
Cattle shelter and three-year care
20 cattle; capital only ₹54.24 L
₹72.62 LDetails